Tri-State Tollway, Roadway Reconstruction and Widening, Hinsdale Oasis (M.P. 25.0) to Ogden Avenue (M.P. 27.8)
Client
Illinois State Highway Tollway Authority
Project Year
2022-2027
Services
- Construction engineering and management
- Transportation Engineering
Solutions Group
- Infrastructure
Phase III Engineering Services for Construction Inspection and Documentation for the reconstruction and lane widening of the I-294 expressway from Hinsdale Oasis to 47th Street and from 47th Street to Ogden Ave. Scope of work includes, Portland Cement Concrete (PCC) & Warm-Mix Asphalt (WMA) paving operations, storm sewer & drainage installations, erosion & sediment control, landscaping & fencing plans, concrete wall pours, pavement marking, attenuator work, traffic switch controls, and submitting various Tollway documentations, such as Inspector Daily Reports, Traffic Control Inspection Reports, IDOT Bituminous Records, and ticket quantities.